Energy Services Agreement for first facility
Company: Applied Digital - Project: Jamestown
The claim, verbatim
Applied Digital entered into an Amended and Restated Energy Services Agreement to supply 100 MW of electricity for co-hosting customers at its first facility.
Source (primary)
Applied Digital 424B3 filed 2022-09-27 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “We entered into an Amended and Restated Energy Services Agreement for the purpose of supplying 100 megawatts ("MW") of electricity to be used by our co-hosting customers at this facility.”
How we checked this
Checked on September 22, 2026. The cited source supports every part of this claim.
The document states the agreement supplies 100 MW for co-hosting customers at the first facility.
Confirmed in the source:
- APLD entered into an Amended and Restated Energy Services Agreement to supply 100 MW of electricity for co-hosting customers at its first facility
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487922000044/a9262022424b3finalprospect.htm) in full (350,225 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 424B3 filed 2022-09-27
Quote: “We entered into an Amended and Restated Energy Services Agreement for the purpose of supplying 100 megawatts ("MW") of electricity to be used by our co-hosting customers at this facility.”