Four customers signed for hosting services
Company: Applied Digital - Project: Jamestown
The claim, verbatim
Entered into agreements with 4 customers for hosting services accounting for total available energy at first facility and 85MW at second facility
Source (primary)
Applied Digital S-1/A filed 2021-12-01 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “We have also entered into agreements with 4 customers which will account for the total available energy under the Amended and Restated Energy Services Agreement at our first facility and 85MW of energy at our second facility once built and able to provide such energy.”
How we checked this
Checked on September 22, 2026. The cited source supports every part of this claim.
The document confirms agreements with four customers covering the first facility's capacity and 85MW at the second facility.
Confirmed in the source:
- the company entered agreements with four hosting customers
- those customers account for the total available energy at the first facility and 85MW at the second facility
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465921145539/tm2124821-5_s1a.htm) in full (502,304 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital S-1/A filed 2021-12-01
Quote: “We have also entered into agreements with 4 customers which will account for the total available energy under the Amended and Restated Energy Services Agreement at our first facility and 85MW of energy at our second facility once built and able to provide such energy.”