First facility online capacity
Company: Applied Digital - Project: Jamestown
The claim, verbatim
First facility in North Dakota is online and providing 55MW of energy and services to customers as of February 2, 2022
Source (primary)
Applied Digital S-1/A filed 2022-04-12 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “as of February 2, 2022 is online and providing 55MW of energy and services to customers”
How we checked this
Checked on September 22, 2026. The cited source supports every part of this claim.
The document states the North Dakota first facility is online providing 55MW as of February 2, 2022.
Confirmed in the source:
- Applied Blockchain's first facility was constructed in North Dakota
- As of February 2, 2022 the first facility is online and providing 55MW of energy and services to customers
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465922044841/tm2132377-23_s1a.htm) in full (563,274 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital S-1/A filed 2022-04-12
Quote: “as of February 2, 2022 is online and providing 55MW of energy and services to customers”