9 MW HPC facility in Jamestown, North Dakota
Company: Applied Digital - Project: Jamestown
What the later record shows
The date slipped
Only initial capacity was energized in 2023. As late as January 2025 the Jamestown HPC facility was still 'nearing completion' at a reduced 7.5 MW, so it missed the H2 2023 target.
“successfully energized initial capacity at the facility. The facility successfully passed the Integrated Systems Test for its first 200KW of HPC equipment and systems”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, North Dakota located adjacent to our 106 MW data center hosting facility.”
2025-01-13 · Applied Digital 10-Q filed 2025-01-14 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
9 MW GPU-optimized HPC facility expected to be brought online in second half of 2023
Source (primary)
Applied Digital 424B5 filed 2023-06-26 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “This facility is expected to be brought online in the second half of calendar year 2023”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The filing describes the Jamestown facility as purpose-built for GPUs to host HPC workloads, with capacity raised from 5 MW to 9 MW. It also says the facility was expected online in the second half of calendar 2023.
Confirmed in the source:
- The Jamestown HPC facility's planned capacity was increased to 9 MW
- The facility was designed and purpose-built for GPUs to host HPC applications
- The facility was expected to be brought online in the second half of calendar year 2023
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000166/apld-preliminaryprospectus.htm) in full (176,255 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 424B5 filed 2023-06-26
Quote: “This facility is expected to be brought online in the second half of calendar year 2023”
delays Applied Digital 10-Q filed 2025-01-14
Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, North Dakota located adjacent to our 106 MW data center hosting facility.”
delays Earnings Release
Quote: “successfully energized initial capacity at the facility. The facility successfully passed the Integrated Systems Test for its first 200KW of HPC equipment and systems”