Jamestown facility temporary power restoration
Company: Applied Digital - Project: Jamestown
What the later record shows
Delivered on time · happened August 31, 2022
The power provider completed repairs in mid-August 2022 and fully restored power. That was ahead of the early-September schedule and within the two-month window.
“The power provider completed the required repairs in mid-August, fully restoring power capacity to Jamestown ahead of the schedule for early September.”
2022-08-25 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Temporary replacement power equipment expected to be installed within approximately two months to restore full capacity
Source (primary)
Applied Digital 8-K filed 2022-07-18 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “replacement equipment on a temporary basis, which is expected to be in place within approximately two months and will serve to restore power to full capacity”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The 8-K states the provider would supply temporary replacement equipment, expected within about two months, that would restore power to full capacity.
Confirmed in the source:
- The power provider for the Jamestown facility determined to provide temporary replacement equipment for the failed substation equipment
- The temporary replacement equipment was expected to be in place within approximately two months
- The temporary equipment was expected to restore power to full capacity
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487922000005/apld-20220712.htm) in full (4,664 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 8-K filed 2022-07-18
Quote: “replacement equipment on a temporary basis, which is expected to be in place within approximately two months and will serve to restore power to full capacity”
confirms Earnings Release
Quote: “The power provider completed the required repairs in mid-August, fully restoring power capacity to Jamestown ahead of the schedule for early September.”