jain.com

Jamestown HPC facility capacity increase

Company: Applied Digital - Project: Jamestown

Subject kind
facility capacity
Statement date
2023-08-01
Promised amount
9.0 MW
Current status
stated

The claim, verbatim

Increased capacity of GPU-optimized HPC facility in Jamestown from originally planned 5 MW to 9 MW

Source (primary)

Applied Digital 10-K filed 2023-08-02 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “On December 14, 2022, we announced the beginning of construction of a 5 megawatt ("MW") facility next to the Company's currently operating 100-MW hosting facility in Jamestown, North Dakota. We subsequently determined to increase the capacity of this facility to 9 MW.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital 10-K filed 2023-08-02

Quote: “On December 14, 2022, we announced the beginning of construction of a 5 megawatt ("MW") facility next to the Company's currently operating 100-MW hosting facility in Jamestown, North Dakota. We subsequently determined to increase the capacity of this facility to 9 MW.”

View cached copy (2026-09-13)Live source ↗