jain.com

Current data center hosting capacity

Company: Applied Digital - Project: Jamestown

Subject kind
facility capacity
Statement date
2024-10-22
Promised amount
286.0 MW
Current status
stated

The claim, verbatim

Company operates sites in Jamestown (106 MW) and Ellendale (180 MW) with total hosting capacity of approximately 286 MW

Source (primary)

Applied Digital S-1 filed 2024-10-23 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We currently operate sites in Jamestown and Ellendale, North Dakota, with a total hosting capacity of approximately 286 MW: ●Jamestown, North Dakota: 106 MW facility. ●Ellendale, North Dakota: 180 MW facility.”

How we checked this

Attempted on September 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315224042178/forms-1.htm) in full (127,290 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-1 filed 2024-10-23

Quote: “We currently operate sites in Jamestown and Ellendale, North Dakota, with a total hosting capacity of approximately 286 MW: ●Jamestown, North Dakota: 106 MW facility. ●Ellendale, North Dakota: 180 MW facility.”

View cached copy (2026-08-31)Live source ↗