Loan advance schedule

Company: Applied Digital - Project: Jamestown

Subject kind
financing
Statement date
2022-08-11
Promised amount
3000000.0 USD
Current status
stated

The claim, verbatim

Initial advance of $12 million (80% of principal) made at closing; remaining $3 million (20%) available upon proof of 100% intended operating capacity of Jamestown facility

Source (primary)

Applied Digital 8-K filed 2022-08-12 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “The first advance on the Loan was made at the time the Loan was entered into and was not to exceed 80% of the total principal amount of the Loan, or $12,000,000.00. The remaining 20% balance of this Loan shall be available for advance following Borrower's proof of 100% intended operating capacity of its Jamestown, North Dakota hosting facility”

How we checked this

Checked on September 22, 2026. The cited source supports every part of this claim.

The document confirms the $12 million (80%) initial advance at closing and the $3 million (20%) balance contingent on proof of full operating capacity.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000162828022022599/apld-20220725.htm) in full (6,667 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 8-K filed 2022-08-12

Quote: “The first advance on the Loan was made at the time the Loan was entered into and was not to exceed 80% of the total principal amount of the Loan, or $12,000,000.00. The remaining 20% balance of this Loan shall be available for advance following Borrower's proof of 100% intended operating capacity of its Jamestown, North Dakota hosting facility”