Jamestown facility permanent power restoration
Company: Applied Digital - Project: Jamestown
What the later record shows
Delivered on time · happened August 31, 2022
Later filings say the power provider completed the required substation repairs in mid-August 2022 and that there were no service interruptions afterward. That is well before Q2 2023, though the passages do not explicitly say the original equipment was returned to service.
“The power provider completed the required repairs in mid-August, fully restoring power capacity to Jamestown ahead of the schedule for early September.”
2022-10-11 · Applied Digital 10-Q filed 2022-10-12 View cached copy (2026-09-13)Live source ↗
“There have been no reductions or interruptions in service since that time and February 28, 2023.”
2023-04-05 · Applied Digital 10-Q filed 2023-04-06 View cached copy (2026-09-13)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Original substation equipment expected to be repaired and returned to service during Q2 2023
Source (primary)
Applied Digital 8-K filed 2022-07-18 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “The repaired original equipment is expected to be returned to service during the second calendar quarter of 2023.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The 8-K says the provider would repair the damaged substation equipment and expected to return it to service in the second calendar quarter of 2023.
Confirmed in the source:
- The original equipment at the substation powering the Jamestown facility was damaged and was to be repaired
- The repaired original equipment was expected to return to service during the second calendar quarter of 2023
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487922000005/apld-20220712.htm) in full (4,664 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 8-K filed 2022-07-18
Quote: “The repaired original equipment is expected to be returned to service during the second calendar quarter of 2023.”
confirms Applied Digital 10-Q filed 2023-04-06
Quote: “There have been no reductions or interruptions in service since that time and February 28, 2023.”
confirms Applied Digital 10-Q filed 2022-10-12
Quote: “The power provider completed the required repairs in mid-August, fully restoring power capacity to Jamestown ahead of the schedule for early September.”