Marathon Digital additional capacity

Company: Applied Digital - Project: Jamestown

Subject kind
customer
Statement date
2023-05-16
Promised amount
39.6 MW
Current status
stated

The claim, verbatim

Marathon added 39.6 MW of additional hosting capacity at Jamestown, North Dakota facility

Source (primary)

Applied Digital S-3 filed 2023-05-17 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Marathon has subsequently added 39.6 MW of additional capacity at the Company's Jamestown, North Dakota facility.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital S-3 filed 2023-05-17

Quote: “Marathon has subsequently added 39.6 MW of additional capacity at the Company's Jamestown, North Dakota facility.”

View cached copy (2026-09-13)Live source ↗