Jamestown HPC facility online date
Company: Applied Digital - Project: Jamestown
What the later record shows
The date slipped
Only an initial 200 kW was energized in July 2023. Filings from October 2024 and January 2025 still describe the Jamestown HPC facility (now 7.5 MW) as 'nearing completion', so it was not done by end of 2023. No new date was given.
“successfully energized initial capacity at the facility. The facility successfully passed the Integrated Systems Test for its first 200KW of HPC equipment and systems”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, North Dakota located adjacent to our 106 MW data center hosting facility.”
2025-01-13 · Applied Digital 10-Q filed 2025-01-14 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
9 MW HPC facility in Jamestown, North Dakota expected to be brought online in H2 2023
Source (primary)
Applied Digital 8-K filed 2023-06-26 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “This facility is expected to be brought online in the second half of calendar year 2023.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The filing describes the Jamestown, North Dakota HPC facility, later expanded to 9 MW, and says it was expected to come online in the second half of calendar 2023.
Confirmed in the source:
- The HPC facility is in Jamestown, North Dakota
- The facility's capacity was increased from 5 MW to 9 MW
- The facility was expected to be brought online in the second half of calendar year 2023
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000163/apld-20230626.htm) in full (11,186 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 8-K filed 2023-06-26
Quote: “This facility is expected to be brought online in the second half of calendar year 2023.”
delays Applied Digital 10-Q filed 2025-01-14
Quote: “The first facility, which is nearing completion, is a 7.5 MW facility in Jamestown, North Dakota located adjacent to our 106 MW data center hosting facility.”
delays Earnings Release
Quote: “successfully energized initial capacity at the facility. The facility successfully passed the Integrated Systems Test for its first 200KW of HPC equipment and systems”