150 MW fourth building (ELN-04) at Polaris Forge 1
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
Net proceeds will fund construction of 150 megawatts of critical IT load at the fourth building (ELN-04) at Polaris Forge 1 in Ellendale, North Dakota
Source (primary)
applied-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-06)Live source ↗
Quote: “fund the construction and associated expenses of 150 megawatts of critical IT load at the fourth building ("ELN-04") at Polaris Forge 1, Applied Digital's AI Factory campus at Ellendale, North Dakota”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms applied-digital 8-K exhibit (ex99-1.htm)
Quote: “fund the construction and associated expenses of 150 megawatts of critical IT load at the fourth building ("ELN-04") at Polaris Forge 1, Applied Digital's AI Factory campus at Ellendale, North Dakota”