jain.com

HPC Hosting - 100 MW facility operational Q4 2025

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2025-10-09
Promised by
2025-12-31
Promised amount
100.0 MW
Current status
verified

What the later record shows

Delivered on time · happened October 31, 2025

The first 100 MW facility at Polaris Forge 1 became operational in October 2025, meeting the Q4 2025 target.

“delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”
2026-01-06 · applied-digital 8-K exhibit (apldq226earningsrelease.htm) View cached copy (2026-09-22)Live source ↗
“The first 100 MW building at Polaris Forge 1 became operational in October 2025.”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

First 100 MW facility at Polaris Forge 1 expected to be operational in calendar Q4 2025 with technical fit-out underway

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Our first 100 MW facility at Polaris Forge 1 remains on track to be operational in calendar Q4 2025, with technical fit-out activities underway this quarter and continuing into next.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The HPC Hosting Update states both the timeline and the ongoing fit-out.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/131/applied-digital-reports-fiscal-first-quarter-2026-results/) in full (34,764 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Our first 100 MW facility at Polaris Forge 1 remains on track to be operational in calendar Q4 2025, with technical fit-out activities underway this quarter and continuing into next.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms applied-digital 8-K exhibit (apldq226earningsrelease.htm)

Quote: “delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”

View cached copy (2026-09-22)Live source ↗

confirms Earnings Release

Quote: “The first 100 MW building at Polaris Forge 1 became operational in October 2025.”

View cached copy (2026-10-08)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.