Polaris Forge 1 ELN-02 Operations
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
Polaris Forge 1 first HPC data center (ELN-02) recently commenced operations with 100 MW capacity
Source (primary)
Applied Digital S-3 filed 2025-12-05 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We recently commenced operations at our first HPC data center at our Polaris Forge 1 campus in Ellendale, ND ("Polaris Forge 1") with 100MW of capacity ("ELN-02").”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Applied Digital S-3 filed 2025-12-05
Quote: “We recently commenced operations at our first HPC data center at our Polaris Forge 1 campus in Ellendale, ND ("Polaris Forge 1") with 100MW of capacity ("ELN-02").”