jain.com

Polaris Forge 1 ELN-02 Operations

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility capacity
Statement date
2025-12-04
Promised amount
100.0 MW
Current status
stated

The claim, verbatim

Polaris Forge 1 first HPC data center (ELN-02) recently commenced operations with 100 MW capacity

Source (primary)

Applied Digital S-3 filed 2025-12-05 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We recently commenced operations at our first HPC data center at our Polaris Forge 1 campus in Ellendale, ND ("Polaris Forge 1") with 100MW of capacity ("ELN-02").”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital S-3 filed 2025-12-05

Quote: “We recently commenced operations at our first HPC data center at our Polaris Forge 1 campus in Ellendale, ND ("Polaris Forge 1") with 100MW of capacity ("ELN-02").”

View cached copy (2026-08-31)Live source ↗