Polaris Forge 1 Building 2 Phase 1 ready for service

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2026-10-08
Promised amount
75.0 MW
Event date
2026-07-01
Current status
stated

What the later record shows

Not a promise: a reported event · happened July 1, 2026

The claim, made on 2026-10-08, reports that Building 2 Phase 1 (75 MW) had already become ready for service on July 1. P5 states this plainly.

“Phase 1 of Building 2 at Polaris Forge 1, representing 75 MW, became ready for service on July 1, lifting live capacity at the campus to 175 MW.”
2026-10-08 · Applied Digital Q1 Earnings Miss on Higher Costs, Revenues Beat - Yahoo Finance View cached copy (2026-10-09)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Phase 1 of Building 2 at Polaris Forge 1 (75 MW) became ready for service on July 1, lifting live campus capacity to 175 MW.

Source (primary)

Applied Digital Q1 Earnings Miss on Higher Costs, Revenues Beat - Yahoo Finance (-, news_article)
View cached copy (2026-10-09)Live source ↗

Quote: “Phase 1 of Building 2 at Polaris Forge 1, representing 75 MW, became ready for service on July 1, lifting live capacity at the campus to 175 MW.”

How we checked this

Checked on October 14, 2026. The cited source supports every part of this claim.

The article reports each of these details.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://finance.yahoo.com/markets/stocks/articles/applied-digital-q1-earnings-miss-140100245.html) in full (12,813 characters, retrieved October 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital Q1 Earnings Miss on Higher Costs, Revenues Beat - Yahoo Finance

Quote: “Phase 1 of Building 2 at Polaris Forge 1, representing 75 MW, became ready for service on July 1, lifting live capacity at the campus to 175 MW.”

View cached copy (2026-10-09)Live source ↗

confirms Applied Digital Q1 Earnings Miss on Higher Costs, Revenues Beat - Zacks Investment Research

Quote: “Phase 1 of Building 2 at Polaris Forge 1, representing 75 MW, became ready for service on July 1, lifting live capacity at the campus to 175 MW”

View cached copy (2026-10-10)Live source ↗Archive.org ↗

Record of changes

October 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.