jain.com

Polaris Forge 1 second 150 MW building

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2025-10-09
Promised by
2026-06-30
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered late · happened October 1, 2026

The next 150 MW building was delivered in phases on July 1 and October 1, 2026. Full delivery came after the mid-2026 target.

“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction began on the next 150 MW building at Polaris Forge 1, scheduled for mid-2026.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗

Quote: “Our second 150 MW facility is scheduled for mid-2026”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release reports that construction began on the next 150 MW building and that it is scheduled for mid-2026.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/131/applied-digital-reports-fiscal-first-quarter-2026-results/) in full (34,802 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Our second 150 MW facility is scheduled for mid-2026”

View cached copy (2026-09-29)Live source ↗

confirms Earnings Release

Quote: “Our second 150 MW facility is scheduled for mid-2026”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Our second 150 MW facility is scheduled for mid-2026”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Our second 150 MW facility is scheduled for mid-2026”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

confirms EX-99.1

Quote: “Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 30, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2025-10-09.
October 9, 2026 — verified