Ellendale 100 MW HPC building ready for service 2H CY2025
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Delivered on time · happened October 31, 2025
The first 100 MW Ellendale building reached ready-for-service on schedule and became operational in October 2025, within 2H 2025.
“delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”
2026-01-06 · applied-digital 8-K exhibit (apldq226earningsrelease.htm) View cached copy (2026-09-22)Live source ↗
“The first 100 MW building at Polaris Forge 1 became operational in October 2025.”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Construction of the first 100 MW, 369,000+ sq ft liquid-cooled HPC facility in Ellendale, ND remains on schedule and the building will be ready for service in the second half of calendar 2025.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release describes the first 100 MW, 369,000+ sq ft liquid-cooled Ellendale HPC building as on schedule. It also says the building will be ready in the second half of 'this calendar year', which is 2025 given the April 14, 2025 release date.
Confirmed in the source:
- Applied Digital broke ground on its first 100 MW HPC facility in Ellendale, North Dakota
- The building is 369,000+ square feet
- The building will provide liquid-cooled infrastructure for HPC applications
- Construction remains on schedule
- The building will be ready for service in the second half of calendar 2025 (the release, dated April 14, 2025, says 'this calendar year')
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/121/applied-digital-reports-fiscal-third-quarter-2025-results/) in full (33,151 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”
confirms Earnings Release
Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”
confirms Earnings Release
Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”
confirms Earnings Release
Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”
confirms applied-digital 8-K exhibit (apldq226earningsrelease.htm)
Quote: “delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”
confirms Earnings Release
Quote: “The first 100 MW building at Polaris Forge 1 became operational in October 2025.”