Ellendale 100 MW HPC building ready for service 2H CY2025

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2025-04-14
Promised by
2025-12-31
Promised amount
100.0 MW
Current status
verified

What the later record shows

Delivered on time · happened October 31, 2025

The first 100 MW Ellendale building reached ready-for-service on schedule and became operational in October 2025, within 2H 2025.

“delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”
2026-01-06 · applied-digital 8-K exhibit (apldq226earningsrelease.htm) View cached copy (2026-09-22)Live source ↗
“The first 100 MW building at Polaris Forge 1 became operational in October 2025.”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction of the first 100 MW, 369,000+ sq ft liquid-cooled HPC facility in Ellendale, ND remains on schedule and the building will be ready for service in the second half of calendar 2025.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release describes the first 100 MW, 369,000+ sq ft liquid-cooled Ellendale HPC building as on schedule. It also says the building will be ready in the second half of 'this calendar year', which is 2025 given the April 14, 2025 release date.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/121/applied-digital-reports-fiscal-third-quarter-2025-results/) in full (33,151 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”

View cached copy (2026-10-03)Live source ↗

confirms Earnings Release

Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

confirms applied-digital 8-K exhibit (apldq226earningsrelease.htm)

Quote: “delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”

View cached copy (2026-09-22)Live source ↗

confirms Earnings Release

Quote: “The first 100 MW building at Polaris Forge 1 became operational in October 2025.”

View cached copy (2026-10-08)Live source ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 30, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2025-04-14.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.