$2.35B 9.25% senior secured notes due 2030

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
financing
Statement date
2026-01-07
Promised by
2030-12-31
Promised amount
2350000000.0 USD
Current status
stated

The claim, verbatim

Completed a $2.35 billion private offering of 9.25% senior secured notes due 2030 at 97% of par, with Morgan Stanley as lead; proceeds for ELN-02 and ELN-03 construction, SMBC Loan repayment, and debt service reserves.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “Completed a $2.35 billion private offering of 9.25% senior secured notes due 2030, issued at 97% of par”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The highlights give the size, coupon, maturity, issue price and use of proceeds, and the management commentary names Morgan Stanley as lead.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/142/applied-digital-reports-fiscal-second-quarter-2026-results/) in full (45,597 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Completed a $2.35 billion private offering of 9.25% senior secured notes due 2030, issued at 97% of par”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Completed a $2.35 billion private offering of 9.25% senior secured notes due 2030, issued at 97% of par, with proceeds allocated to construction of the 100 MW (ELN‑02) and 150 MW (ELN‑03) facilities at Polaris Forge 1, repayment of the SMBC Loan, and establishment of required debt service reserves.”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Completed a $2.35 billion private offering of 9.25% senior secured notes due 2030, issued at 97% of par, with proceeds allocated to construction of the 100 MW (ELN‑02) and 150 MW (ELN‑03) facilities at Polaris Forge 1, repayment of the SMBC Loan, and establishment of required debt service reserves.”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Completed a $2.35 billion private offering of 9.25% senior secured notes due 2030, issued at 97% of par”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2026-01-07.