Polaris Forge 1 second 150 MW building mid-2026
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Delivered late · happened October 1, 2026
The second 150 MW building reached full capacity in two 75 MW phases, on July 1 and October 1, 2026. Both dates are after the mid-2026 schedule.
“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
“we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”
2026-10-07 · View PDF View cached copy (2026-10-08)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Construction has begun on the next 150 MW building at Polaris Forge 1, which is scheduled for mid-2026.
Source (primary)
applied-digital 8-K exhibit (apldq126earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-29)Live source ↗
Quote: “Our second 150 MW facility is scheduled for mid-2026”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release says Applied Digital began construction on the next 150 MW building at Polaris Forge 1 and that this second 150 MW facility is scheduled for mid-2026.
Confirmed in the source:
- Construction has begun on the next 150 MW building at Polaris Forge 1
- The second 150 MW facility at Polaris Forge 1 is scheduled for mid-2026
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487925000068/apldq126earningsrelease.htm) in full (33,636 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms applied-digital 8-K exhibit (apldq126earningsrelease.htm)
Quote: “Our second 150 MW facility is scheduled for mid-2026”
confirms View PDF
Quote: “we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”
confirms EX-99.1
Quote: “Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”