Polaris Forge 1 second 150 MW building mid-2026

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2025-10-08
Promised by
2026-06-30
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered late · happened October 1, 2026

The second 150 MW building reached full capacity in two 75 MW phases, on July 1 and October 1, 2026. Both dates are after the mid-2026 schedule.

“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
“we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”
2026-10-07 · View PDF View cached copy (2026-10-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction has begun on the next 150 MW building at Polaris Forge 1, which is scheduled for mid-2026.

Source (primary)

applied-digital 8-K exhibit (apldq126earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-29)Live source ↗

Quote: “Our second 150 MW facility is scheduled for mid-2026”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release says Applied Digital began construction on the next 150 MW building at Polaris Forge 1 and that this second 150 MW facility is scheduled for mid-2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487925000068/apldq126earningsrelease.htm) in full (33,636 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (apldq126earningsrelease.htm)

Quote: “Our second 150 MW facility is scheduled for mid-2026”

View cached copy (2026-09-29)Live source ↗

confirms View PDF

Quote: “we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”

View cached copy (2026-10-08)Live source ↗

confirms EX-99.1

Quote: “Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 30, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.