Polaris Forge 1 full buildout 400 MW
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
At full buildout, the Polaris Forge 1 campus is contracted to deliver 400 MW of critical IT load.
Source (primary)
Applied Digital Activates 75 MW of AI Infrastructure at North Dakota Campus - TheEnergyMag (-, news_article)
View cached copy (2026-10-09)Live source ↗Archive.org ↗
Quote: “At full buildout, the campus is contracted to deliver 400 MW of critical IT load.”
How we checked this
Checked on October 14, 2026. The cited source supports every part of this claim.
The article states that at full buildout the Polaris Forge 1 campus is contracted to deliver 400 MW of critical IT load.
Confirmed in the source:
- At full buildout, the Polaris Forge 1 campus is contracted to deliver 400 MW of critical IT load
What we did: Read our cached copy of the publisher (https://www.theenergymag.com/news/market-news/applied-digital-activates-75-mw-ai-infrastructure) in full (2,391 characters, retrieved October 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital Activates 75 MW of AI Infrastructure at North Dakota Campus - TheEnergyMag
Quote: “At full buildout, the campus is contracted to deliver 400 MW of critical IT load.”