The claim, verbatim
CoreWeave contracted for an additional 150 MW at the expanded Polaris Forge 1 campus in Ellendale, North Dakota
Source (primary)
Applied Digital DEF 14A filed 2026-09-25 (SEC EDGAR, sec_filing)
View cached copy (2026-09-26)Live source ↗
Quote: “expanding our Polaris Forge 1 campus in Ellendale, North Dakota, with CoreWeave taking an additional 150 MW”
How we checked this
Checked on September 28, 2026. The cited source supports every part of this claim.
The proxy says Polaris Forge 1 in Ellendale was expanded with CoreWeave taking an additional 150 MW, and describes this as a third CoreWeave lease for 150MW.
Confirmed in the source:
- CoreWeave took an additional 150 MW at the Polaris Forge 1 campus
- Polaris Forge 1 is in Ellendale, North Dakota
- The Polaris Forge 1 campus was expanded
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315226044325/formdef14a.htm) in full (278,076 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital DEF 14A filed 2026-09-25
Quote: “expanding our Polaris Forge 1 campus in Ellendale, North Dakota, with CoreWeave taking an additional 150 MW”