Polaris Forge 1 first 100 MW in service Oct 2025

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2026-09-25
Promised amount
100.0 MW
Event date
2025-10-31
Current status
stated

What the later record shows

Not a promise: a reported event · happened October 31, 2025

Said in September 2026, the claim reports that the first 100 MW facility had already been brought into service in October 2025.

“The company brought its first 100 MW high-performance computing facility into service at Polaris Forge 1 in October 2025.”
2026-09-25 · Applied Digital Alabama Data Center Is Confirmed, but Brookwood Still Has Questions - remio View cached copy (2026-09-28)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Applied Digital brought its first 100 MW HPC facility into service at Polaris Forge 1 in October 2025.

Source (primary)

Applied Digital Alabama Data Center Is Confirmed, but Brookwood Still Has Questions - remio (-, news_article)
View cached copy (2026-09-28)Live source ↗Archive.org ↗

Quote: “The company brought its first 100 MW high-performance computing facility into service at Polaris Forge 1 in October 2025.”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The article states that Applied Digital brought its first 100 MW high-performance computing facility into service at Polaris Forge 1 in October 2025.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.remio.ai/post/applied-digital-alabama-data-center-is-confirmed-but-brookwood-still-has-questio) in full (26,155 characters, retrieved September 28, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital Alabama Data Center Is Confirmed, but Brookwood Still Has Questions - remio

Quote: “The company brought its first 100 MW high-performance computing facility into service at Polaris Forge 1 in October 2025.”

View cached copy (2026-09-28)Live source ↗Archive.org ↗

Record of changes

September 28, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 29, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.