Polaris Forge 1 total capacity
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
Polaris Forge 1, the Ellendale, North Dakota datacenter campus, has 400MW of capacity
Source (primary)
Applied Digital 8-K filed 2025-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “the Company's 400 MW Ellendale, North Dakota datacenter campus ("Polaris Forge 1")”
How we checked this
Checked on September 17, 2026. The cited source supports every part of this claim.
The filing describes Polaris Forge 1 as the Company's 400 MW Ellendale, North Dakota datacenter campus.
Confirmed in the source:
- Polaris Forge 1 is Applied Digital's datacenter campus in Ellendale, North Dakota
- Polaris Forge 1 has 400MW of capacity
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315225012458/form8-k.htm) in full (9,993 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 8-K filed 2025-08-29
Quote: “the Company's 400 MW Ellendale, North Dakota datacenter campus ("Polaris Forge 1")”