Polaris Forge 1 third HPC facility timeline
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
Applied Digital has a third 150 MW HPC data center anticipated at Polaris Forge 1 in calendar 2027.
Source (primary)
applied-digital 8-K exhibit (apldq326earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-10)Live source ↗
Quote: “A second 150 MW HPC data center is under construction at the same campus and is expected to come online in calendar 2026, while a third 150 MW facility is anticipated in calendar 2027.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms applied-digital 8-K exhibit (apldq326earningsrelease.htm)
Quote: “A second 150 MW HPC data center is under construction at the same campus and is expected to come online in calendar 2026, while a third 150 MW facility is anticipated in calendar 2027.”