Polaris Forge 1 Building 2 Phase 1 RFS
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Not a promise: a reported event · happened July 1, 2026
The claim reports Phase 1 of Building 2 reaching Ready for Service on July 1, 2026, an event that had already happened; the company's earnings release states the same date.
“Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW.”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity to 175 MW.
Source (primary)
Applied Digital Reports Fiscal First Quarter 2027 Results - Applied Digital Corporation (APLD) (-, news_article)
View cached copy (2026-10-08)Live source ↗Archive.org ↗
Quote: “Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The release states the 75 MW Phase 1 delivery on July 1, 2026 and the resulting 175 MW of live capacity at the campus.
Confirmed in the source:
- Phase 1 of Building 2 at Polaris Forge 1 was delivered Ready for Service
- Phase 1 of Building 2 at Polaris Forge 1 is 75 MW
- Phase 1 of Building 2 at Polaris Forge 1 was delivered on July 1, 2026
- After Phase 1 of Building 2, total live capacity at the Polaris Forge 1 campus was 175 MW
What we did: Read our cached copy of the publisher (https://ir.applieddigital.com/news-events/press-releases/detail/163/applied-digital-reports-fiscal-first-quarter-2027-results) in full (41,009 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital Reports Fiscal First Quarter 2027 Results - Applied Digital Corporation (APLD)
Quote: “Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW”