jain.com

Recover >$300M equity in Ellendale HPC Campus

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
financing
Statement date
2025-01-14
Promised amount
300000000.0 USD
Current status
stated

The claim, verbatim

MAM investment plus future project financing expected to repay project-level debt and let the company recover over an estimated $300 million of its equity investment in the Ellendale HPC Campus.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “allow the Company to recover over an estimated $300 million of its equity investment in the Ellendale HPC Campus”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The press release says the MAM investment and future project financing will be used to repay project-level debt and let the company recover over an estimated $300 million of its Ellendale HPC Campus equity.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/118/applied-digital-reports-fiscal-second-quarter-2025-results/) in full (35,889 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “allow the Company to recover over an estimated $300 million of its equity investment in the Ellendale HPC Campus”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “allow the Company to recover over an estimated $300 million of its equity investment in the Ellendale HPC Campus”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “allow the Company to recover over an estimated $300 million of its equity investment in the Ellendale HPC Campus”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “allow the Company to recover over an estimated $300 million of its equity investment in the Ellendale HPC Campus”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2025-01-14.