jain.com

ELN-03 data center capacity

Company: Applied Digital

Subject kind
facility capacity
Statement date
2025-11-13
Promised amount
150.0 MW
Current status
stated

The claim, verbatim

ELN-03 data center facility has 150 MW capacity at Polaris Forge 1 campus in Ellendale, North Dakota

Source (primary)

applied-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-26)Live source ↗

Quote: “150 MW data centers, ELN-02 and ELN-03 (the "Facilities"), at Applied Digital's 400 MW Ellendale, North Dakota data center campus ("Polaris Forge 1")”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms applied-digital 8-K exhibit (ex99-1.htm)

Quote: “150 MW data centers, ELN-02 and ELN-03 (the "Facilities"), at Applied Digital's 400 MW Ellendale, North Dakota data center campus ("Polaris Forge 1")”

View cached copy (2026-09-26)Live source ↗