Ellendale 100 MW HPC facility under construction
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
The Company broke ground on its first 100 MW, 369,000-square-foot liquid-cooled HPC facility in Ellendale, North Dakota.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “During the fiscal second quarter, the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 369,000-square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release says the company broke ground on the 100 MW, 369,000-square-foot, liquid-cooled HPC facility in Ellendale.
Confirmed in the source:
- Applied Digital broke ground on its first 100 MW HPC facility in Ellendale, North Dakota
- The building is 369,000 square feet
- The facility provides liquid-cooled infrastructure for HPC applications
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/105/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (35,062 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “During the fiscal second quarter, the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 369,000-square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”
confirms Earnings Release
Quote: “the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 369,000-square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”
confirms Earnings Release
Quote: “During the fiscal second quarter, the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 369,000-square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”
confirms Earnings Release
Quote: “During the fiscal second quarter, the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 369,000-square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”