jain.com

Ellendale 100 MW HPC facility under construction

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility capacity
Statement date
2024-08-28
Promised amount
100.0 MW
Current status
stated

The claim, verbatim

The Company broke ground on its first 100 MW, 369,000-square-foot liquid-cooled HPC facility in Ellendale, North Dakota.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “During the fiscal second quarter, the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 369,000-square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release says the company broke ground on the 100 MW, 369,000-square-foot, liquid-cooled HPC facility in Ellendale.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/105/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (35,062 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “During the fiscal second quarter, the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 369,000-square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 369,000-square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”

View cached copy (2026-10-03)Live source ↗

confirms Earnings Release

Quote: “During the fiscal second quarter, the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 369,000-square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “During the fiscal second quarter, the Company broke ground on its first 100 MW high-performance compute facility in Ellendale, North Dakota. The new 369,000-square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2024-08-28.