Polaris Forge 1 Building 1 delivery

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2025-10-21
Promised by
2025-12-31
Promised amount
100.0 MW
Current status
verified

What the later record shows

Delivered on time · happened October 31, 2025

The investor presentation labels the 100 MW building PF1-1 / Building 1 and shows it as energized. Later releases say it became operational in October 2025; some 10-Qs say November 2025. Either date falls within 2025.

“The first 100 MW building at Polaris Forge 1 became operational in October 2025.”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗
“PF1-1 100 MW Energized PF1-2 150 MW Calendar - 2H 2026 (16)”
2026-10-08 · Investor Presentation View cached copy (2026-10-08)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Polaris Forge 1 Building 1 (100 MW capacity) expected to be delivered in 2025

Source (primary)

applied-digital 8-K exhibit (apld_invxfinalpresentati.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗

Quote: “Building 1 (100 MW) - Expected Deliver Date 2025”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

Applied Digital's October 2025 investor presentation lists Polaris Forge 1 Building 1 at 100 MW with an expected delivery date of 2025, specified elsewhere as the second half of 2025.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487925000076/apld_invxfinalpresentati.htm) in full (26,833 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (apld_invxfinalpresentati.htm)

Quote: “Building 1 (100 MW) - Expected Deliver Date 2025”

View cached copy (2026-09-27)Live source ↗

confirms Earnings Release

Quote: “The first 100 MW building at Polaris Forge 1 became operational in October 2025.”

View cached copy (2026-10-08)Live source ↗

confirms Investor Presentation

Quote: “PF1-1 100 MW Energized PF1-2 150 MW Calendar - 2H 2026 (16)”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 27, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 28, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.