Building 2 Phase 1 operational June 30 2026
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Not a promise: a reported event · happened July 1, 2026
The claim reports Phase 1 Ready for Service as already achieved. The company's later releases date that event to July 1, 2026, not June 30.
“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Phase 1 of Building 2's additional 75 MW reached Ready for Service on June 30, 2026
Source (primary)
APLD Slides 36% in 3 Months: Should Investors Exit or Hold the Stock? - TradingView (-, news_article)
View cached copy (2026-09-08)Live source ↗Archive.org ↗
Quote: “Phase 1 of Building 2's additional 75 MW reaching Ready for Service on June 30, 2026”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The article states that Phase 1 of Building 2's additional 75 MW reached Ready for Service on June 30, 2026.
Confirmed in the source:
- Phase 1 of Building 2 covers an additional 75 MW
- Phase 1 of Building 2 reached Ready for Service on June 30, 2026
What we did: Read our cached copy of the publisher (https://www.tradingview.com/news/zacks:93c7d203a094b:0-apld-slides-36-in-3-months-should-investors-exit-or-hold-the-stock/) in full (10,319 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms APLD Slides 36% in 3 Months: Should Investors Exit or Hold the Stock? - TradingView
Quote: “Phase 1 of Building 2's additional 75 MW reaching Ready for Service on June 30, 2026”