Current operational capacity

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility capacity
Statement date
2026-10-03
Promised amount
100.0 MW
Current status
stated

The claim, verbatim

Only 100 MW is currently operational (Polaris Forge 1 Building 1) out of 1.51 GW under construction.

Source (primary)

Investor Presentation (IR page (ir.applieddigital.com), ir_presentation)
View cached copy (2026-10-03)Live source ↗Archive.org ↗

Quote: “today we have just 100 MW operational out of 1.51 GW under construction”

How we checked this

Checked on October 5, 2026. The cited source supports every part of this claim.

The presentation says 'today we have just 100 MW operational out of 1.51 GW under construction' and its pipeline slide identifies the operating 100 MW as Polaris Forge 1 Building 1.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/_assets/_dc3803b9c1b927b47c1b631f6696dc2c/appliedblockchaininc/db/2905/27269/pdf/APLD_INV_June2026_Updated-compressed.pdf) in full (47,679 characters, retrieved October 3, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “today we have just 100 MW operational out of 1.51 GW under construction”

View cached copy (2026-10-03)Live source ↗Archive.org ↗