jain.com

Polaris Forge 1 total live capacity 175 MW

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility capacity
Statement date
2026-07-27
Promised amount
175.0 MW
Current status
stated

The claim, verbatim

Total live capacity at Polaris Forge 1 campus is 175 MW as of June 30, 2026.

Source (primary)

EX-99.1 (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗

Quote: “bringing the total live capacity at the campus to 175 MW.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The release says the June 30, 2026 delivery brought total live capacity at the campus to 175 MW.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/sec-filings/all-sec-filings/content/0001144879-26-000044/apldq426earningsreleaseasf.htm) in full (54,584 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms EX-99.1

Quote: “bringing the total live capacity at the campus to 175 MW.”

View cached copy (2026-09-01)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2026-07-27.