jain.com

Macquarie up to $900 million investment in Ellendale HPC campus

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
financing
Statement date
2025-01-14
Promised amount
900000000.0 USD
Current status
stated

The claim, verbatim

Funds managed by Macquarie Asset Management will invest up to $900 million in Applied Digital's Ellendale HPC data center campus

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Funds managed by MAM to invest up to $900 million in the Company's Ellendale HPC data center campus (the "Ellendale HPC Campus").”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The release states that funds managed by MAM will invest up to $900 million in the Ellendale HPC campus.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/118/applied-digital-reports-fiscal-second-quarter-2025-results/) in full (35,851 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Funds managed by MAM to invest up to $900 million in the Company's Ellendale HPC data center campus (the "Ellendale HPC Campus").”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Funds managed by MAM to invest up to $900 million in the Company’s Ellendale HPC data center campus”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Funds managed by MAM to invest up to $900 million in the Company’s Ellendale HPC data center campus”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Funds managed by MAM to invest up to $900 million in the Company’s Ellendale HPC data center campus”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Funds managed by MAM to invest up to $900 million in the Company’s Ellendale HPC data center campus”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-01-14.