jain.com

HPC Ellendale Facility under construction

Company: Applied Digital - Project: Polaris Forge 1

This claim was marked delayed on September 4, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2024-05-30
Promised by
2025-01-01
Promised amount
100.0 MW
Current status
delayed

The claim, verbatim

Company commenced construction of 100 MW HPC datacenter in Ellendale, North Dakota in 2023, expected to become operational in early calendar year 2025

Source (primary)

Applied Digital S-1 filed 2024-05-31 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “In 2023, we commenced the construction of our first 100 MW HPC datacenter in Ellendale, North Dakota (the "HPC Ellendale Facility"). We plan to continue building this datacenter in 2024... we anticipate that this business segment will begin generating meaningful revenues once the HPC Ellendale Facility becomes operational, which is expected sometime in the early calendar year 2025.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital S-1 filed 2024-05-31

Quote: “In 2023, we commenced the construction of our first 100 MW HPC datacenter in Ellendale, North Dakota (the "HPC Ellendale Facility"). We plan to continue building this datacenter in 2024... we anticipate that this business segment will begin generating meaningful revenues once the HPC Ellendale Facility becomes operational, which is expected sometime in the early calendar year 2025.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.