jain.com

HPC Ellendale facility under construction

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2024-08-29
Promised amount
100.0 MW
Current status
stated

The claim, verbatim

The company broke ground on a 100 MW HPC data center in Ellendale, North Dakota

Source (primary)

Applied Digital 10-K filed 2024-08-30 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The Company also broke ground on a 100 MW HPC data center in project in Ellendale, ND”

How we checked this

Checked on September 18, 2026. The cited source supports every part of this claim.

The filing states the company broke ground on a 100 MW HPC data center project in Ellendale, ND.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487924000216/apld-20240531.htm) in full (481,620 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 10-K filed 2024-08-30

Quote: “The Company also broke ground on a 100 MW HPC data center in project in Ellendale, ND”

View cached copy (2026-08-31)Live source ↗