HPC Ellendale Operational Start

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2024-05-16
Promised by
2025-01-01
Current status
verified

What the later record shows

Delivered late · happened October 31, 2025

The HPC Ellendale facility (now the first Polaris Forge 1 building) became operational in October 2025 rather than early calendar 2025. The 10-K confirms the segment began generating meaningful revenue once it was operational in fiscal 2026.

“The first lease is for the full capacity of our 100 MW data center that was completed and became operational in October 2025”
2026-01-07 · Applied Digital 10-Q filed 2026-01-08 View cached copy (2026-08-31)Live source ↗
“This business segment began generating meaningful revenues once the first HPC building within Polaris Forge 1 became operational in fiscal year 2026.”
2026-07-29 · View 10-K View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

HPC Ellendale Facility expected to become operational in early calendar year 2025 and begin generating meaningful revenues once operational

Source (primary)

Applied Digital 424B5 filed 2024-05-17 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We anticipate that this business segment will begin generating meaningful revenues once the HPC Ellendale Facility becomes operational, which is expected sometime in the early calendar year 2025”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The prospectus supplement states both the expected early calendar 2025 operational timing and that meaningful revenues were anticipated once the facility became operational.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487924000132/preferredcapitalprospectus.htm) in full (178,920 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 424B5 filed 2024-05-17

Quote: “We anticipate that this business segment will begin generating meaningful revenues once the HPC Ellendale Facility becomes operational, which is expected sometime in the early calendar year 2025”

View cached copy (2026-08-31)Live source ↗

confirms Applied Digital 10-Q filed 2026-01-08

Quote: “The first lease is for the full capacity of our 100 MW data center that was completed and became operational in October 2025”

View cached copy (2026-08-31)Live source ↗

confirms View 10-K

Quote: “This business segment began generating meaningful revenues once the first HPC building within Polaris Forge 1 became operational in fiscal year 2026.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.