CoreWeave leases ELN-02 and ELN-03 at Polaris Forge 1

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
customer
Statement date
2026-07-28
Promised amount
250.0 MW
Current status
stated

The claim, verbatim

On May 28, 2025, subsidiaries entered into data center leases with CoreWeave to deliver an aggregate of 250 MW of capacity at Polaris Forge 1

Source (primary)

Applied Digital 10-K filed 2026-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗

Quote: “On May 28, 2025, our subsidiaries APLD ELN-02 LLC and APLD ELN-03 LLC each entered into a data center lease with CoreWeave, Inc. to deliver an aggregate of 250 MW of capacity”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital 10-K filed 2026-07-29

Quote: “On May 28, 2025, our subsidiaries APLD ELN-02 LLC and APLD ELN-03 LLC each entered into a data center lease with CoreWeave, Inc. to deliver an aggregate of 250 MW of capacity”

View cached copy (2026-08-30)Live source ↗