CoreWeave leases ELN-02 and ELN-03 at Polaris Forge 1
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
On May 28, 2025, subsidiaries entered into data center leases with CoreWeave to deliver an aggregate of 250 MW of capacity at Polaris Forge 1
Source (primary)
Applied Digital 10-K filed 2026-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗
Quote: “On May 28, 2025, our subsidiaries APLD ELN-02 LLC and APLD ELN-03 LLC each entered into a data center lease with CoreWeave, Inc. to deliver an aggregate of 250 MW of capacity”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Applied Digital 10-K filed 2026-07-29
Quote: “On May 28, 2025, our subsidiaries APLD ELN-02 LLC and APLD ELN-03 LLC each entered into a data center lease with CoreWeave, Inc. to deliver an aggregate of 250 MW of capacity”