Building 4 capacity
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
Building 4 at Polaris Forge 1 will have 150MW of data center capacity
Source (primary)
Applied Digital 8-K filed 2025-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “Building 4 at Polaris Forge 1 ("Building 4"), a 150MW data center to be constructed by the Company”
How we checked this
Checked on September 17, 2026. The cited source supports every part of this claim.
The filing describes Building 4 at Polaris Forge 1 as a 150MW data center to be constructed by the Company.
Confirmed in the source:
- Building 4 is located at Polaris Forge 1
- Building 4 is a 150MW data center to be constructed by the Company
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315225012458/form8-k.htm) in full (9,993 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 8-K filed 2025-08-29
Quote: “Building 4 at Polaris Forge 1 ("Building 4"), a 150MW data center to be constructed by the Company”