Ellendale building 369,000+ square feet

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility capacity
Statement date
2025-04-14
Promised by
2025-12-31
Promised amount
369000.0 square feet
Current status
verified

What the later record shows

Delivered on time · happened October 31, 2025

P1 identifies the 369,000+ sq ft liquid-cooled building as the first 100 MW facility at Polaris Forge 1, and later passages say that facility became operational in October 2025. No later passage restates the final square footage.

“The Company’s first 100 MW HPC facility at the Polaris Forge 1 campus in Ellendale, North Dakota—a 369,000+ square-foot building—is expected to offer ultra-low-cost, highly efficient liquid-cooled infrastructure”
2025-07-30 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The first 100 MW building at Polaris Forge 1 became operational in October 2025.”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The building will be 369,000+ square feet and provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “The new 369,000+ square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The release describes the new building as over 369,000 square feet, providing ultra-low-cost, highly efficient liquid-cooled infrastructure for HPC applications.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/121/applied-digital-reports-fiscal-third-quarter-2025-results/) in full (33,113 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “The new 369,000+ square-foot building will provide ultra-low-cost and highly efficient liquid-cooled infrastructure for HPC applications.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “The first 100 MW building at Polaris Forge 1 became operational in October 2025.”

View cached copy (2026-10-08)Live source ↗

confirms Earnings Release

Quote: “The Company’s first 100 MW HPC facility at the Polaris Forge 1 campus in Ellendale, North Dakota—a 369,000+ square-foot building—is expected to offer ultra-low-cost, highly efficient liquid-cooled infrastructure”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-04-14.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.