Extension of exclusivity under hyperscaler LOI for Ellendale HPC campus

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
partnership
Statement date
2024-08-28
Event date
2024-07-26
Current status
stated

What the later record shows

Not a promise: a reported event · happened July 26, 2024

The claim reports an exclusivity extension signed on July 26, 2024, which was already done when it was stated on 2024-08-28.

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

On July 26, 2024, Applied Digital entered into an agreement extending the exclusivity period under the LOI for leasing its Ellendale, North Dakota HPC data center campus.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “On July 26, 2024, Applied Digital Corporation entered into an agreement extending the exclusivity period under the previously announced LOI for leasing the Company's Ellendale, North Dakota HPC data center campus.”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The press release states that on July 26, 2024, the Company extended the exclusivity period under the previously announced LOI for leasing its Ellendale, North Dakota HPC campus.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/105/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (35,062 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “On July 26, 2024, Applied Digital Corporation entered into an agreement extending the exclusivity period under the previously announced LOI for leasing the Company's Ellendale, North Dakota HPC data center campus.”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 7, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2024-08-28.
October 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.