Polaris Forge 1 total planned capacity
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
Polaris Forge 1 campus will comprise three data centers totaling 400 MW: 100 MW, 150 MW, and a third 150 MW facility
Source (primary)
Applied Digital 10-K filed 2025-07-30 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “These facilities are purpose built for high power density GPUs and along with a third 150 MW data center, will comprise our Polaris Forge 1 campus.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Applied Digital 10-K filed 2025-07-30
Quote: “These facilities are purpose built for high power density GPUs and along with a third 150 MW data center, will comprise our Polaris Forge 1 campus.”