jain.com

Entry into lease with hyperscaler for 100MW Building A

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2025-01-07
Promised by
2027-12-31
Current status
stated

The claim, verbatim

Company to enter into a lease with a hyperscaler for the 100MW data center Building A at Ellendale, North Dakota

Source (primary)

Applied Digital 8-K/A filed 2025-01-08 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “the Company's entry into a lease (the "Lease") with a hyperscaler for the 100MW data center building located on the Company's Ellendale, North Dakota campus ("Building A")”

How we checked this

Attempted on September 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315225001423/form8-ka.htm) in full (9,263 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 8-K/A filed 2025-01-08

Quote: “the Company's entry into a lease (the "Lease") with a hyperscaler for the 100MW data center building located on the Company's Ellendale, North Dakota campus ("Building A")”

View cached copy (2026-08-31)Live source ↗