Ellendale 100 MW HPC building ready for service H2 2025
Company: Applied Digital
What the later record shows
Delivered on time · happened October 31, 2025
The FY2026 10-K says the first 100 MW HPC data center at Polaris Forge 1 in Ellendale became operational in October 2025. The Q2 release says Ready-for-Service was achieved on schedule. Both are within the H2 2025 promise.
“The Company’s first 100 MW HPC facility at the Polaris Forge 1 campus in Ellendale, North Dakota—a 369,000+ square-foot building”
2025-07-30 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“Achieved Ready‑for‑Service at Polaris Forge 1, delivering 100 MW on schedule and fully energizing the first building (ELN-02)”
2026-01-06 · applied-digital 8-K exhibit (apldq226earningsrelease.htm) View cached copy (2026-09-22)Live source ↗
“Our first HPC data center at the campus, with approximately 100 MW of critical IT load, became operational in October 2025.”
2026-07-29 · View 10-K View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Construction of the first 100 MW HPC facility in Ellendale, North Dakota is on schedule, and the building will be ready for service in the second half of calendar 2025.
Source (primary)
applied-digital 8-K exhibit (apldq325earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-17)Live source ↗
Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms applied-digital 8-K exhibit (apldq325earningsrelease.htm)
Quote: “Construction remains on schedule and the building will be ready for service in the second half of this calendar year.”
confirms View 10-K
Quote: “Our first HPC data center at the campus, with approximately 100 MW of critical IT load, became operational in October 2025.”
confirms applied-digital 8-K exhibit (apldq226earningsrelease.htm)
Quote: “Achieved Ready‑for‑Service at Polaris Forge 1, delivering 100 MW on schedule and fully energizing the first building (ELN-02)”
confirms Earnings Release
Quote: “The Company’s first 100 MW HPC facility at the Polaris Forge 1 campus in Ellendale, North Dakota—a 369,000+ square-foot building”