100 MW Polaris Forge 1 facility operational Q4 2025
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Delivered on time · happened October 31, 2025
Later filings and releases state the first 100 MW building at Polaris Forge 1 became operational in October 2025, within the promised Q4 2025. The January 2026 release says ready-for-service was achieved on schedule. One 10-Q passage says November 2025, which is still on time.
“delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”
2026-01-06 · applied-digital 8-K exhibit (apldq226earningsrelease.htm) View cached copy (2026-09-22)Live source ↗
“The first 100 MW building at Polaris Forge 1 became operational in October 2025.”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
First 100 MW facility at Polaris Forge 1 remains on track to be operational in calendar Q4 2025
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗
Quote: “Our first 100 MW facility at Polaris Forge 1 remains on track to be operational in calendar Q4 2025”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release states the first 100 MW facility at Polaris Forge 1 remains on track to be operational in calendar Q4 2025.
Confirmed in the source:
- The first 100 MW facility at Polaris Forge 1 remains on track to be operational in calendar Q4 2025
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/131/applied-digital-reports-fiscal-first-quarter-2026-results/) in full (34,802 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “Our first 100 MW facility at Polaris Forge 1 remains on track to be operational in calendar Q4 2025”
confirms applied-digital 8-K exhibit (apldq226earningsrelease.htm)
Quote: “delivering 100 MW on schedule and fully energizing the first building (ELN-02), marking completion of the first of three contracted buildings”
confirms Earnings Release
Quote: “The first 100 MW building at Polaris Forge 1 became operational in October 2025.”