Second 150MW facility at Polaris Forge 1 operational mid-2026
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Delivered late · happened October 1, 2026
Building 2 (150 MW) came online in two phases: 75 MW on July 1, 2026 and the remaining 75 MW on October 1, 2026. The full 150 MW was therefore operational after the mid-2026 (June 30) target, and only half had been delivered on July 1.
“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗
“On October 1, 2026, the Company achieved Ready for Service for the second 75 MW phase of Building 2 at Polaris Forge 1”
2026-10-07 · Earnings Release View cached copy (2026-10-08)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
A second 150 megawatt HPC facility at Polaris Forge 1 is scheduled to come online in mid-2026.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “a second 150 MW facility scheduled to come online in mid-2026”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The CEO's statement about Polaris Forge 1 says a second 150 MW facility is scheduled to come online in mid-2026.
Confirmed in the source:
- A second 150 MW facility at Polaris Forge 1 is scheduled to come online in mid-2026
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/126/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (41,830 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “a second 150 MW facility scheduled to come online in mid-2026”
confirms Earnings Release
Quote: “Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”