Polaris Forge 1 second 150MW facility online

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2025-07-30
Promised by
2026-06-30
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered late · happened October 1, 2026

The second 150 MW facility came online in phases on July 1 and October 1, 2026. Both dates are later than mid-2026.

“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
“we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”
2026-10-07 · View PDF View cached copy (2026-10-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Second 150 MW facility at Polaris Forge 1 scheduled to come online in mid-2026; construction already underway.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “a second 150 MW facility scheduled to come online in mid-2026”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release gives a mid-2026 online date for the second 150 MW facility and separately says construction on it is already underway.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/126/applied-digital-reports-fiscal-fourth-quarter-and-full-year/) in full (41,868 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “a second 150 MW facility scheduled to come online in mid-2026”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “a second 150 MW facility scheduled to come online in mid-2026”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “a second 150 MW facility scheduled to come online in mid-2026”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “a second 150 MW facility scheduled to come online in mid-2026”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

confirms EX-99.1

Quote: “Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

confirms View PDF

Quote: “we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”

View cached copy (2026-10-08)Live source ↗

Record of changes

September 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 30, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-29 was the source's retrieval date; source published 2025-07-30.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.