jain.com

Extended LOI exclusivity period for Ellendale campus

Company: Applied Digital - Project: Polaris Forge 1

This claim was marked delayed on September 3, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2024-08-28
Promised by
2024-07-26
Current status
delayed

The claim, verbatim

Entered into agreement on July 26, 2024 extending exclusivity period under LOI for leasing Ellendale HPC data center campus

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “On July 26, 2024, Applied Digital Corporation entered into an agreement extending the exclusivity period under the previously announced LOI for leasing the Company's Ellendale, North Dakota HPC data center campus.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “On July 26, 2024, Applied Digital Corporation entered into an agreement extending the exclusivity period under the previously announced LOI for leasing the Company's Ellendale, North Dakota HPC data center campus.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed