jain.com

Ellendale HPC expansion to 400 MW total

Company: Applied Digital

Subject kind
facility capacity
Statement date
2026-09-25
Promised amount
300.0 MW
Current status
stated

The claim, verbatim

Plan to bring an additional 300 MW online through two additional buildings in design stage, increasing Ellendale total HPC capacity to 400 MW

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗

Quote: “we plan to bring an extra 300 MW online through two additional buildings currently in the design stage. This will ultimately increase Ellendale's total HPC capacity to 400 MW.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “we plan to bring an extra 300 MW online through two additional buildings currently in the design stage. This will ultimately increase Ellendale's total HPC capacity to 400 MW.”

View cached copy (2026-09-25)Live source ↗Archive.org ↗