Polaris Forge 1 second building (150MW) operational mid-2026
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Delivered late · happened October 1, 2026
The second 150 MW building became fully operational only when its second 75 MW phase was delivered on October 1, 2026. That is after the expected mid-2026 date.
“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
“we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”
2026-10-07 · View PDF View cached copy (2026-10-08)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The second building, expected to house a 150MW data center, is under construction and expected to be operational in mid-2026.
Source (primary)
applied-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-04)Live source ↗
Quote: “the second building, which is expected to house a 150MW data center, is currently under construction and is expected to be operational in the middle of 2026”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release states the second building, expected to house a 150MW data center, is currently under construction and expected to be operational in the middle of 2026.
Confirmed in the source:
- The second building at Polaris Forge 1 is expected to house a 150MW data center
- The second building was under construction as of the Aug. 29, 2025 release
- The second building is expected to be operational in mid-2026
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000149315225012458/ex99-1.htm) in full (7,542 characters, retrieved October 4, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms applied-digital 8-K exhibit (ex99-1.htm)
Quote: “the second building, which is expected to house a 150MW data center, is currently under construction and is expected to be operational in the middle of 2026”
confirms View PDF
Quote: “we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”
confirms EX-99.1
Quote: “Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”