Polaris Forge 1 second building (150MW) operational mid-2026

Company: Applied Digital - Project: Polaris Forge 1

Subject kind
facility timeline
Statement date
2025-08-28
Promised by
2026-06-30
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered late · happened October 1, 2026

The second 150 MW building became fully operational only when its second 75 MW phase was delivered on October 1, 2026. That is after the expected mid-2026 date.

“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
“we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”
2026-10-07 · View PDF View cached copy (2026-10-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The second building, expected to house a 150MW data center, is under construction and expected to be operational in mid-2026.

Source (primary)

applied-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-04)Live source ↗

Quote: “the second building, which is expected to house a 150MW data center, is currently under construction and is expected to be operational in the middle of 2026”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release states the second building, expected to house a 150MW data center, is currently under construction and expected to be operational in the middle of 2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000149315225012458/ex99-1.htm) in full (7,542 characters, retrieved October 4, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (ex99-1.htm)

Quote: “the second building, which is expected to house a 150MW data center, is currently under construction and is expected to be operational in the middle of 2026”

View cached copy (2026-10-04)Live source ↗

confirms View PDF

Quote: “we began commencing operations at our second HPC data center at our Polaris Forge 1 campus, which reached its full 150MW of capacity as of the date of filing”

View cached copy (2026-10-08)Live source ↗

confirms EX-99.1

Quote: “Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

October 4, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 5, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.