Polaris Forge 1 Building 2 Phase 2 RFS
Company: Applied Digital - Project: Polaris Forge 1
What the later record shows
Not a promise: a reported event · happened October 1, 2026
The claim was made on 2026-10-07 and reports an RFS milestone that had already occurred on October 1, 2026. The earnings materials confirm the second phase was delivered on October 1, bringing live capacity to 250 MW.
“Building 2 (150 MW) was delivered in two 75 MW phases, the first on July 1, 2026 and the second on October 1 subsequent to quarter end, bringing live capacity at the campus to 250 MW”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
“Delivered the second 75 MW phase of Building 2 at Polaris Forge 1 Ready for Service, bringing total live capacity at the campus to 250 MW”
2026-10-07 · EX-99.1 View cached copy (2026-10-08)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Achieved Ready for Service for the second 75 MW phase of Building 2 at Polaris Forge 1 on October 1, 2026, bringing operational critical IT load to 250 MW across two buildings and 10 data halls.
Source (primary)
Applied Digital Reports Fiscal First Quarter 2027 Results - Applied Digital Corporation (APLD) (-, news_article)
View cached copy (2026-10-08)Live source ↗Archive.org ↗
Quote: “On October 1, 2026, the Company achieved Ready for Service for the second 75 MW phase of Building 2 at Polaris Forge 1, bringing fully operational critical IT load at the campus to 250 MW”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The release states the October 1, 2026 milestone and the resulting 250 MW across two buildings and 10 data halls.
Confirmed in the source:
- The second 75 MW phase of Building 2 at Polaris Forge 1 achieved Ready for Service
- The second phase of Building 2 achieved Ready for Service on October 1, 2026
- Fully operational critical IT load at the Polaris Forge 1 campus reached 250 MW
- The 250 MW at Polaris Forge 1 spans two buildings
- The 250 MW at Polaris Forge 1 spans 10 data halls
What we did: Read our cached copy of the publisher (https://ir.applieddigital.com/news-events/press-releases/detail/163/applied-digital-reports-fiscal-first-quarter-2027-results) in full (41,009 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital Reports Fiscal First Quarter 2027 Results - Applied Digital Corporation (APLD)
Quote: “On October 1, 2026, the Company achieved Ready for Service for the second 75 MW phase of Building 2 at Polaris Forge 1, bringing fully operational critical IT load at the campus to 250 MW”